Recently, Pukou District officials issued a report on the implementation of Pukou District’s 2020 National Economic and Social Development Plan and the 2021 National Economic and Social Development Plan (Draft) :

Among them, the draft explains in detail the 2021 national economic and social development plan, especially the school construction issue, which is of particular concern to everyone. Let’s take a look at it together.

PART01

Pukou Health Housing Group is responsible for the construction of three schools in Pukou South Center (one for junior high school, one for primary school and one for kindergarten). At present, they have passed the evaluation meeting of feasibility research experts, and are handling the opinion letter of site selection pre-examination and feasibility research approval. The construction is planned to start in September this year and be completed in June 2023.

 

At the fifth meeting of the Fourth People’s Congress of Pukou District, Nanjing City, 10 key practical projects of people’s livelihood in 2021 were selected through the voting procedure. Among them, the most notable one is that three educational institutions, including kindergarten, primary school and middle school, will be built in the No. 4 and No. 5 areas in the south center of the city.

The construction of the three schools of Chengnan Center is scheduled to start in September 2021 and be completed in June 2023. The total investment is about 53 million, covering an area of about 5,300 square meters. The scale is 3 rails and 9 classes.

With a total investment of about 190 million yuan and an area of about 22,300 square meters, the primary school in No. 4 of Chengnan Center has 18 classes and 3 tracks.

The total investment of the middle school located in No.5 of the South Center is about 330 million, covering an area of about 37,800 square meters, with a scale of 8 tracks and 24 classes.

These schools are located in the north of the south center of the city, between Zhengrong Runtang Mansion and Wangjiang Yueyue Mansion. The locations are as follows:

These plates have been erupting this year...

PART02

Pukou High-tech Zone is responsible for the construction of the High School Attached to the South Art Institute. Currently, the architectural design scheme of the school has been determined and the bidding for EPC general contractor is under way. The construction is expected to start in the first half of 2021 and the construction is scheduled to be completed in June 2023.

I showed it on the public resources trading platform of Nanjing. The High School Affiliated to the South Art School issued the bidding announcement for the general contract of the project, and the start time and completion time were exposed!

Construction is expected to start in March this year and be completed by August 15, 2022.

On December 10th last year, the project of Pukou New Campus of Secondary Art School Affiliated to Nanjing University of the Arts was officially launched.

In provinces and cities, nanjing college of art and so on various strength, under the support of pukou agency staff will give full play to the pukou high-tech zone of gold medal, gold, gold housekeeper service supermarket three “gold medal” advantage, establish a special working team, perfect service system, with high quality and efficiency to speed up project construction, focus on the south into a landmark of the affiliated high school of art and people’s livelihood project!

 

The project of the South Art Attached High School was launched when the site of the 25-12 primary school site (A33A) was converted into a secondary professional school (A32).

These plates have been erupting this year...

The total land area of the project is about 43,200 square meters, and supporting facilities such as teaching and training rooms, teaching auxiliary and administrative rooms, living rooms, art sharing space, social motorized garage and underground parking lot are planned to be built. The total construction area is about 641.9791 million square meters, and the aboveground construction area is about 40,883.19 square meters.